As the country's designated "three bases and one channel" (a large-scale oil production and processing base, a large-scale coal, coal power, and coal chemical industry base, a large-scale wind power base, and a national energy resource land-based transportation channel), Xinjiang has, in recent years, relied on its unique resource advantages and adhered to technological innovation as the leading force, promoting the clean, low-carbon, and efficient utilization of traditional energy and the vigorous development of the new energy industry. It has been striding forward on the path from "green" to "new".
Recently, the reporter visited the carbon dioxide mixed-phase drive pilot test station in the 530 well area of the Second Oil Production Plant of Xinjiang Oilfield. As the technicians clicked on the mouse on the computer, the control valve of a white capsule-shaped storage tank beside the oil well slowly opened, and a continuous flow of carbon dioxide was injected into the underground depths along the pipeline.
This is the first CCUS demonstration project of Xinjiang Oilfield's conglomerate reservoir.
"CCUS means capturing and purifying the carbon dioxide emitted during oil production, and then injecting it into the new production process for reuse and storage. The traditional water injection drive oil method can only extract a part of the oil, while injecting carbon dioxide for oil production can significantly improve the extraction efficiency." Wang Chunhui, the production supervision group leader of the natural gas treatment station of the Second Oil Production Plant, introduced. The annual injection of carbon dioxide in this well area is 520,000 tons, with a carbon storage rate of 85%, and the daily oil production has increased from 12 tons before carbon injection to more than 100 tons now.
From "water injection drive oil" to "carbon injection drive oil", a difference of just one character reflects a deep adjustment of the energy production mode. Data shows that since this year, Xinjiang Oilfield has injected 985,000 tons of carbon, an increase of 200,000 tons compared to the same period last year, with a daily injection capacity of over 4,000 tons. Since 2020, Xinjiang Oilfield has cumulatively injected over 3 million tons of carbon.
The "clean substitution" of heavy oil extraction is recognized as the most difficult "hard nut to crack". The traditional heavy oil thermal recovery process requires injecting steam into the formation, and the steam injection boiler consumes a large amount of natural gas. According to statistics, the heavy oil production of Xinjiang Oilfield accounts for about 30% of the total crude oil production, but the energy consumption during the production process accounts for about 80% of the total energy consumption of the oilfield.
To break through the high energy consumption problem in heavy oil extraction, Xinjiang Oilfield has continuously explored new paths for green transformation.
In September 2025, the Fengcheng Oilfield operation area of Xinjiang Oilfield completed the world's first demonstration project of tower-type photothermal substitution for ultra-heavy oil extraction. This project uses over 20,000 heliostats to reflect sunlight to a 113-meter-high absorption tower, generating 305°C high-temperature steam for ultra-heavy oil extraction. It can supply 52,300 tons of high-quality superheated steam per year, replacing 3.92 million cubic meters of natural gas.
In December of the same year, the world's first 110-kilovolt solid storage type electric steam injection boiler was officially put into operation in the Heavy Oil Development Company of Xinjiang Oilfield. "Previously, it was burning gas, now it is consuming electricity. This boiler is like a 'green charging battery', combining green electricity with the overheat steam injection boiler of the oilfield, providing 160,000 tons of high-quality overheat steam per year, replacing 13 million cubic meters of natural gas, and reducing about 25,000 tons of carbon dioxide emissions," said Yang Bin, a first-level engineer of the Heavy Oil Development Company.
Old oilfields have been rejuvenated, and oil fields need to be built on coal fields.
Hami City is a truly "energy treasure trove". The predicted total resource quantity of coal in the area exceeds 57 billion tons, and the already proven rich oil coal resource quantity exceeds 6.4 billion tons. In March 2024, the world's first direct liquefaction coal-to-oil project using second-generation technology was started in Barikun County, Hami City. This is Xinjiang's first coal-to-oil project, planning to use 14.2 million tons of coal per year to produce 4 million tons of oil products. This is equivalent to the production volume of the largest ultra-deep oilfield in China - Fu Man Oilfield in 2023. According to the overall plan, this area's long-term annual oil production will reach 10 million tons, equivalent to the creation of a new large oilfield, which will play an important role in ensuring national energy security.