The first batch of electrochemical energy storage power station projects of the Yantai Energy Storage Center, located in Laizhou, Shandong Province, were led by Shanghai Electric Environmental Group (Mechanical and Electrical Institute). Different from many energy storage projects that only focus on power regulation functions, this power station took into account ecological protection, local people's livelihood, and long-term sustainable operation from the very beginning, expanding the value of energy storage beyond simply storing electricity.
Site selection prioritizes ecological relief
During the site selection stage, the project fully considered the impact on the surrounding natural environment, actively avoiding various ecologically sensitive areas, and choosing to build on existing public facilities land. The natural ground elevation of the station site is between 48 and 53 meters, higher than the 100-year flood level, and no additional flood control facilities are needed, directly reducing the investment in earthwork and supporting projects.
After the construction of the project is completed, the project's vegetation restoration plan can increase the greening coverage of the station area to over 35%. Through vegetation replanting and ecological restoration methods, the environmental disturbance caused during the construction phase can be mitigated, while the energy storage facilities are being implemented, and the regional ecological bottom line is maintained.
A combination of short-term and long-term energy storage, balancing efficiency and safety
To adapt to the current situation of tight peak-load resources in the local power grid and the high pressure of wind and solar power consumption in Shandong Province, the project adopts a mixed energy storage route combining lithium iron phosphate and all-vanadium liquid flow batteries. The two technologies each perform their own duties, covering different time periods of regulation needs.
The project is equipped with 95MW/190MWh lithium iron phosphate energy storage units, using 314Ah high-capacity cells, effectively improving the group efficiency, compared to the conventional scheme, it increases by 20%. In addition, it is equipped with 5MW/20MWh all-vanadium liquid flow battery units, relying on a long cycle life of 20,000 times, undertaking long-term energy storage regulation tasks, compensating for the shortcomings of short-term energy storage technologies in long-term continuous discharge scenarios.
Safety management is the core环节 of electrochemical energy storage projects. This scheme sets up multiple protection mechanisms. PACK-level detection combined with cabin-level fire protection systems, using perfluorohexane and compressed air foam for coordinated firefighting, can maintain the suppression duration of re-ignition at 24 hours. A proactive safety early warning platform is also provided, which can detect signs of thermal runaway 48 hours in advance. During the trial operation phase of the project, this system identified a local overheating hazard, providing a safety barrier for stable operation.
Multiple benefits are realized, balancing emission reduction and local value
After the project is officially put into operation, it can accept and consume 150GWh of wind power and photovoltaic electricity annually, corresponding to an emission reduction of approximately 52,000 tons of carbon dioxide. The energy storage system adopts a liquid cooling cooling scheme, which is 30% more energy-efficient compared to the traditional air cooling scheme, and the water consumption is reduced by 40% simultaneously. During the operation phase, it continuously reduces resource consumption.
The project also brings tangible social benefits to the local area. During the construction period, a total of 200 jobs were released, with local workers accounting for 60%. In the operation stage, the project will also establish a technical training base, planning to complete 500 hours of energy storage-related training. With the commissioning of the power station, the peak-load adjustment space of the regional power grid is expanded, which can stably guarantee the electricity supply for 100,000 residents in Yantai, reduce the risk of power outages, and improve power supply reliability.
The project also builds a digital ESG management platform and sets up 1,000 monitoring points. Carbon emission-related data can be summarized and uploaded in real time to meet the requirements of compliance disclosure. The project has also been selected as an encouraged project list for lithium batteries in Shandong Province.
Planning for the entire life cycle,打通 battery recycling chain
During the project planning stage, the construction party also planned the full life cycle management scheme for energy storage batteries, thinking ahead about the disposal path for batteries after retirement. Batteries reaching the service life are prioritized for secondary utilization, such as being used in backup power supplies with lower performance requirements. Batteries that need to be dismantled and recycled are processed using wet methods to extract internal metal materials, with a material recovery rate exceeding 90%.
After the electrolyte generated from the dismantling of lithium iron phosphate batteries is processed, it can be reused as industrial raw materials in the industrial chain, and the battery residual value rate can reach 70%. The project also collaborates with local related enterprises to build a stable recycling supply chain and form a closed-loop recycling system, reducing the environmental pressure caused by battery waste.
Continuous technological iteration is ongoing, and the model is being exported externally.
This energy storage station is more like a replicable hybrid energy storage model. The R&D team has already initiated frontier technology research and is promoting the implementation of the coupling scheme of solid-state batteries and hydrogen energy storage. The goal is to complete a zero-carbon energy supply park by 2027.
This construction and operation model that integrates short-term regulation of lithium iron phosphate batteries and long-term energy storage of vanadium liquid flow is planned to be exported externally, to regions such as Vietnam and Indonesia, to apply the mature hybrid energy storage construction experience from China to more regions with strong demand for new energy development.
From the early stage of site selection, technology selection, to operation emissions reduction, local employment promotion, and battery recycling and future technological iteration, the Yantai Energy Storage Center uses a series of verifiable data to demonstrate the diverse value of the energy storage project. Energy storage is not only a "super charging battery" for the power grid, but can also become an important carrier for ecological protection, industrial circulation, and local power supply guarantee.